So we have approval, what's next?
We are scheduled to break ground on Monday 10/12.  From there, it will be about 3.5 months to complete the house.
1 week for Initial Site work, excavation, and driveway.  
2 weeks for Water service, sewer lateral, electric and electric secondary, basement excavation, basement walls
1 month for Rough Framing, Beams& Sheathed roofing complete  Most windows and exterior doors
1 month for Rough Plumbing & HVAC, Rough Electrical, Insulation, Drywall/Sheet Rock Installed, taped and walls primed.  Exterior Siding.
3 weeks for Concrete Basement Floor, Interior Doors & Trim installed, Cabinets Installed.  Painting and flooring.
3 weeks for Electrical fixtures, counter tops, carpeting, finish plumbing, final rough grade, gutters.  Certificate of Occupancy complete.
MOVE IN!
Throw in a slow down for Thanksgiving and Christmas, and I'm estimating we should be moving around Valentine's Day.