So we have approval, what's next?

We are scheduled to break ground on Monday 10/12. From there, it will be about 3.5 months to complete the house.

1 week for Initial Site work, excavation, and driveway.
2 weeks for Water service, sewer lateral, electric and electric secondary, basement excavation, basement walls
1 month for Rough Framing, Beams& Sheathed roofing complete Most windows and exterior doors
1 month for Rough Plumbing & HVAC, Rough Electrical, Insulation, Drywall/Sheet Rock Installed, taped and walls primed. Exterior Siding.
3 weeks for Concrete Basement Floor, Interior Doors & Trim installed, Cabinets Installed. Painting and flooring.
3 weeks for Electrical fixtures, counter tops, carpeting, finish plumbing, final rough grade, gutters. Certificate of Occupancy complete.

MOVE IN!

Throw in a slow down for Thanksgiving and Christmas, and I'm estimating we should be moving around Valentine's Day.

0 comments:

Our "Scrapbook"

I've never been proficient at scrapbooking, but I wanted a way of capturing the building of our new home. A blog is the perfect way for two "techies" to accomplish the artistry of capturing memories.

We moved from the Midwest to the East Coast in October 2008. We found our building site in November 2008, and broke ground in October 2009.

Henceforth, The Building of Blackthorn Ridge.